Remarks |
Duration |
Owner |
Main Contractor |
Project Name
. |
|
Completed without delay |
10 Months |
SEC-Central |
Z J Engineering & Construction |
Construction of New 132/13.8 KV S/S # 8127. AL-Badiea |
 |
Completed without delay |
6 Months |
SEC-Central |
Z J Engineering & Construction |
Reinforcement of 132/33 KV S/S # 8027. Kind Abdul Aziz Military Academy |
 |
Completed without delay |
8 Months |
SEC-Central |
Trading & Development Partnership |
Construction of New S/S 7919. Hail |
 |
Completed without delay |
14 Months |
SEC-Central |
AL-Babtain Cont. Co |
Construction of New 380KV S/S # 9012. Al-Mursalat, Riyadh |
 |
Under
Construction |
10 Months |
SEC-Central |
Z J Engineering & Construction |
Construction of New 132/13.8KV S/S # 8141 Nahda Riyadh |
 |
Completed without delay |
10 Months |
SEC-Central |
Al-Osais Co. |
Construction of New 132/13.8KV S/S 8829 Unaizah Al-Qassim |
 |
Completed without delay |
10 Months |
SEC-Central |
Al-Osais Co. |
Construction of New 132/13.8KV S/S # 8122 Riyadh |
 |
Completed without delay |
6 Months |
Ministry of Culture |
T.D.P |
Construction of 33-5.5KV Elect. S/S for Riyadh TV Complex |
 |
Completed without delay |
12 Months |
SEC-Central |
T.D.P |
Construction of New 132/13.8 K.V S/S 8506 in Sudair Industrial Area |
 |
Completed without delay |
5 Months |
SEC-Central |
ISCOSA SIEMENS Co. |
Reinforcement of 132/13.8 KV S/S in Miskah Al-Qassim |
 |
Completed without delay |
5 Months |
SEC-Central |
NATEL Co. LTD. |
Extension of Switchgear Room at S/S 8002 at King Khalid International Airport – Riyadh |
 |
Completed |
New Project |
SEC-Central |
Capital Lights Co. |
Construction of New 132/13.8 KV S/S # 8052 East Riyadh |
 |
Completed |
New Project |
SEC-Central |
Coogelex Co. |
Reinforcement of 4 S/S ‘s 8068 Huraymila, 8606 Roshan, 8911 Baqaa & 8922 Hayit |
 |
Completed |
New Project |
SEC-Central |
ISCOSA Industries & Maintenance |
Power Factor Correction in S/s 8914, S/S 8915 & S/s 8918 in Hail Region |
 |
Completed |
New Project |
SEC-Central |
National Contracting Co. (N.C.C) |
Construction of New Switch Station NO. 8073 |
 |
Completed |
Extention |
SEC-Central |
SIEMENS |
Nafl Expansion S/S 9008 380 KV BSP |
 |
Completed |
New Project |
SEC-Central |
Service Solution Co. |
Construction of New Substation No. 8169 AlRabwa |
 |
Completed |
New Project |
SEC-Central |
Al-Arrab Co. |
Construction of New Substation No. 8130 Swaidi |
 |
Completed 90% |
New Project |
SEC-Central |
AL-Babtain Co. |
Construction of New Substation No. 8200 Al-Naseem and 8202 Ghornatha |
 |
Completed |
New Project |
SEC-WOA |
BEMCO |
Construction of New Aziziah-3 Substation |
 |
Completed 85% |
Extention |
SEC-WOA |
BEMCO |
Extension of Taif & Hawaiah Airport |
 |
Completed |
New Project |
SEC-COA |
GE Grid Solution |
Construction of New S/S 8206 Al-Nuzha |
 |
Completed |
New Project |
SEC-COA |
AL-Mashariq |
Construction of 110/13.8 KV Substation Al-Adel – Makkah |
 |
Completed 95% |
New Project |
NG CENTRAL |
GE Grid Solution |
Construction of New S/S 8206 Al-Nuzha |
 |
Completed 95% |
New Project |
NG CENTRAL |
AL-OJAIMI CO. |
Construction of New 132/13.8 KV S/S 8226 Al-
Rawabi
|
 |
Completed 90% |
New Project |
NC CENTRAL |
Larsen & Toubro S.A. LLC |
Construction of New S/S 132/1.8 kV S/S 8308 Al-Fal
Industrial City Riyad
|
 |
Completed 85% |
New Project |
NCC CENTRAL |
Ibn Omairah Co. |
Construction of New S/S 132/13.8 KV S/S 8220 Al-
Nada
|
 |